Electric utility company Southern California Edison (SCE) teamed up with Tesla to bring one of the world’s largest electron-storing solutions to life in less than six months. In fact, it only took three months to go from groundbreaking to running. The urgency came down to a gap in the grid created by the loss of the Aliso Canyon natural gas storage facility.
While getting both a large company like SCE and the local government to move quickly on a project is difficult, Tesla had no problem delivering its large batteries to the site; the Powerpack containers and companion inverters are pretty much plug and play. Once the concrete was poured, the companies installed the system and connected it to the grid.